Recent Certificates of the Secretary of Energy & Environmental Affairs

After the close of the public comment period and on or before the last day of the review period for an Environmental Notification Form (ENF), Environmental Impact Report (EIR) or Notice of Project Change (NPC), the Secretary of Energy & Environmental Affairs issues a written certificate.

For ENFs, the certificate states whether or not an Environmental Impact Report is required and, if so, what is required in the scope. For EIRs, the certificate states whether or not the EIR adequately and properly complies with MEPA and the MEPA regulations. NPC certificates state whether additional MEPA review is warranted.

The following are the most recent Certificates issued by the Secretary of Energy & Environmental Affairs. Click on the name of the project to be linked to a scanned copy of the Certificate. After appearing on this page, these Certificates may be found in the current issue of the Environmental Monitor covering the period during which they were issued. Afterwards, they may be found in the on-line MEPA archives.

Secretary's Certificates through April 18, 2014

Environmental Notification Forms

EEA No.Project NameLocationActionAction Date
13940ADM Tihonet Mixed Use Development – Phase C5: Tihonet East SolarPlymouth, Carver and WarehamDoes not require an Environmental Impact Report04/11/2014
15150Water Treatment PlantChathamDoes not require an Environmental Impact Report04/18/2014
15164Water Treatment PlantNortonDoes not require an Environmental Impact Report04/18/2014
15169New England Executive Park Renovations and ExpansionBurlingtonRequires an Environmental Impact Report04/18/2014
15171MCP Phase IV Remedy ImplementationManchester-by-the-SeaDoes not require an Environmental Impact Report04/11/2014
15172Water’s Edge Nominee Trust ResidenceNantucketDoes not require an Environmental Impact Report04/11/2014
15173Needham MewsNeedhamDoes not require an Environmental Impact Report04/11/2014
15174Black Whale RestaurantNew BedfordDoes not require an Environmental Impact Report04/11/2014
15175Herb Chambers Volvo of NorwoodNorwoodDoes not require an Environmental Impact Report04/11/2014
15177Wareham Station PlatformWarehamDoes not require an Environmental Impact Report04/11/2014
15178WRTA Vehicle Maintenance and Operations FacilityWorcesterDoes not require an Environmental Impact Report04/11/2014

Environmental Impact Reports

No Data Found.

Notices of Project Change

No Data Found.

Records of Decision

EEA No.Project NameLocationComments DueActionAction Date
15169New England Executive Park Renovations and ExpansionBurlington05/07/2014Secretary proposes to grant a Phase 1 Waiver04/18/2014

Special Review Procedures

No Data Found.

Public Benefits Determinations

EEA No.Project NameLocationActionAction Date
15052The Boston GardenBostonSecretary has determined that the project will have a public benefit04/11/2014

Extensions

No Data Found.