The Official Website of the Executive Office of Energy and Environmental Affairs (EOEEA)
Docket:
Docket Details
TypeDocketNameSubjectSummaryFiledClosedCategory
EFSBEFSB13-2/13-151/152National GridPetition of New England Power Company d/b/a National Grid for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectively.Transmission Lines9/20/2013  


Docket Electronic Filings
 DescriptionDateMemoURL
Hearing Schedule4/18/2014Presiding Officer forwards evidentiary hearing schedule to partieshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/41814efsbevhsch.pdf
Cover Letter4/17/2014Counsel for City of Salem files responses to EFSB’s First Set of Information Requestshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/41714slmrspncl.pdf
Responses4/17/2014Counsel for City of Salem files responses to EFSB’s First Set of Information Requestshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/41714slmrspn.pdf
Responses4/17/2014Counsel for NGRID files responses to EFSB’s 4th Set of Information Requests and amended response to EFSB-G-11(e)http://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/41714ngrdrspn.pdf
Responses4/10/2014Counsel for Footprint Power Salem Harbor files responses to EFSB’s First Set of Information Requestshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/41014fpwrrspn.pdf
Cover Letter4/10/2014Counsel for Footprint Power Salem Harbor files responses to EFSB’s First Set of Information Requestshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/41014fpwrrspncl.pdf
Notice of Withdrawal4/10/2014Counsel for HFW files Notice of Withdrawal of representation for Hawthorne Hotel, Finz Seafood & Grill and Waters & Brownhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/41014hfwntwd.pdf
Ruling4/8/2014Presiding Officer forwards Ruling on joint Motion for extension of time to file responses to information requestshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/4814efsbrul.pdf
Joint Motion4/8/2014Counsel for NGRID files joint Motion with City of Salem for extension of time to file responses to information requestshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/4814ngjmtn.pdf
Comments on additional evidentiary dates3/27/2014Counsel for HFW forwards comments on additional evidentiary dateshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/32714hfwcmn.pdf
Cover Letter3/27/2014Presiding Officer forwards 4th Set of Information Requests to NGRIDhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/32714efsbir4ngcl.pdf
4th set of Information Requests to NEP3/27/2014Presiding Officer forwards 4th Set of Information Requests to NGRIDhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/32714efsbir4nep.pdf
Information Request3/27/2014Presiding Officer forwards First Set of Information Requests to City of Salemhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/32714efsbir1slm.pdf
Cover Letter3/27/2014Presiding Officer forwards First Set of Information Requests to City of Salemhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/32714efsbir1slmcl.pdf
Additional Evidentiary Hearing Dates3/27/2014Presiding Officer forwards additional evidentiary hearing dates to partieshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/32714efsbadevhr.pdf
Information Request3/27/2014Presiding Officer forwards First Set of Information Requests to Footprint Powerhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/32714efsbir1fp.pdf
Cover Letter3/27/2014Presiding Officer forwards First Set of Information Requests to Footprint Powerhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/32714efsbir1fpcl.pdf
Confirmation of Hearing Dates to all Parties3/26/2014Presiding Officer sends confirmation of hearing dates to all partieshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/32614efsbcnf.pdf
Email re proposed evidentiary dates3/26/2014Counsel for HFW agrees with initial proposed evidentiary dateshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/32614hfweml.pdf
Comments on Proposed Evidentiary Schedule3/25/2014Counsel for NGRID forwards comments on proposed evidentiary schedulehttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/32514ngcmn.pdf
Proposed Evidentiary Dates3/25/2014Presiding Officer forwards proposed evidentiary dates to partieshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/32514efsbpevdt.pdf
Letter in Support3/21/2014Counsel for HFW supports City of Salem’s direct case and endorses COS-1 being entered into the recordhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/32114hfwltsp.pdf
Direct Testimony3/20/2014Counsel for City of Salem files Pre-filed Direct Testimony of David Knolton (COS-1)http://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/32014slmtst.pdf
Notice of Intent3/3/2014Counsel for HFW files Notice of Intent to present a direct casehttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/3314hfwntint.pdf
 3/3/2014Counsel for City of Salem files Notice of Intent to present a direct case 
Responses (part 1 of 4)2/28/2014Counsel for NGRID files responses to EFSB’s Third Set of Information Requests including a redacted response to EFSB-PA-36; and files responses to City of Salem's (COS) and HFW's First Sets of Information Requestshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/22814ngridrspp1.pdf
Responses (part 2 of 4)2/28/2014Counsel for NGRID files responses to EFSB’s Third Set of Information Requests including a redacted response to EFSB-PA-36; and files responses to City of Salem's (COS) and HFW's First Sets of Information Requestshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/22814ngridrspp2.pdf
Responses (part 3 of 4)2/28/2014Counsel for NGRID files responses to EFSB’s Third Set of Information Requests including a redacted response to EFSB-PA-36; and files responses to City of Salem's (COS) and HFW's First Sets of Information Requestshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/22814ngridrspp3.pdf
Responses (part 4 of 4)2/28/2014Counsel for NGRID files responses to EFSB’s Third Set of Information Requests including a redacted response to EFSB-PA-36; and files responses to City of Salem's (COS) and HFW's First Sets of Information Requestshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/22814ngridrspp4.pdf
Ruling2/25/2014Presiding Officer issues Ruling on Motion to Amend Procedural Schedule, and forwards revised Procedural Schedule to partieshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/22514efsbrul.pdf
Joint Responses2/21/2014Counsel for HFW and City of Salem file joint Response to NGRID’s Opposition to Extension of Procedural Schedulehttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/22114hfwrsp.pdf
Responses2/19/2014Counsel for NGRID files responses to EFSB's Second Set of Information Requestshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/21914ngrdrspefsb2.pdf
Opposition2/18/2014Counsel for NGRID files Opposition to HFW’s and City of Salem’s joint motion to extend the procedural schedulehttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/21814ngridopp.pdf
Information Request2/14/2014Presiding Officer issues Third Set of Information Requests to NGRIDhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/21414efsbir3.pdf
Cover Letter2/14/2014Presiding Officer issues Third Set of Information Requests to NGRIDhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/21414efsbir3cl.pdf
Joint Request2/14/2014Counsel for HFW and City of Salem file joint request to amend the procedural schedule by extending all deadlines after March 3rdhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/21414hfwcosrq.pdf
Cover Letter2/14/2014Counsel for City of Salem files First Set of Information Requests to NGRIDhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/21414slmir1cl.pdf
Information Request2/14/2014Counsel for City of Salem files First Set of Information Requests to NGRIDhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/21414slmir1.pdf
Certificate of Service2/14/2014Counsel for City of Salem files First Set of Information Requests to NGRIDhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/21414slmir1cs.pdf
Information Request2/14/2014Counsel for HFW files First Set of Information Requests to NGRIDhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/21414hfwir1.pdf
Supplemental Responses to EFSB-N-82/12/2014Counsel for NGRID files 2nd supplemental response to EFSB-N-8http://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/21214ngridrsp2.pdf
Notice of Appearance2/7/2014Counsel for HFW files Appearance of J. Raymond Miyares on its behalfhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/2714hfwntap.pdf
Supplemental Responses2/6/2014Counsel for NGRID files supplemental response to EFSB-CM-1, and confidential Attachment EFSB-CM-1(s)http://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/2614ngridsrsp.pdf
 2/4/2014Counsel for NGRID forwards e-mail regarding service of paper copies of Jan. 31st filing 
Supplemental Response to EFSB-PA-121/31/2014Counsel for NGRID files supplemental response to EFSB-PA-12http://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/13114ngridsrsp.pdf
Supplemental Responses1/17/2014Counsel for NGRID files supplemental response to EFSB-N-8 and confidential attachment to samehttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/11714ngsprsp.pdf
Information Request1/13/2014Presiding Officer issues Second Set of Information Requests to NGRIDhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/11314efsbir2.pdf
Cover Letter1/13/2014Presiding Officer issues Second Set of Information Requests to NGRIDhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/11314efsbir2cl.pdf
Attachment to EFSB-V-61/9/2014Counsel for NGRID files Attachment to EFSB-V-6 which was inadvertently omitted from its 11/22/13 filinghttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/1914ngrdrspat.pdf
 1/9/2014Presiding Officer issues Revised Procedural Schedule 
2nd REVISED Procedural Schedule1/9/2014Presiding Officer issues 2nd Revised Procedural Schedulehttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/1914efsb2rvps.pdf
 1/8/2014Counsel for HFW files letter clarifying its request for an extension to the procedural schedule 
Letter1/8/2014Counsel for NGRID advises parties that it does not oppose an extension of the procedural schedulehttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/1814ngdltr.pdf
Amended Procedural schedule and Requests1/7/2014Counsel for Hawthorne Hotel, Finz Seafood & Grill and Waters & Brown (HFW) files amended procedural schedule and requests an extension to the schedulehttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/1714hhfrqu.pdf
REVISED Procedural Schedule1/6/2014Presiding Officer forwards revised procedural schedule reflecting filing deadline of 1/31/14 for supplemental response to EFSB-PA-12http://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/1614efsbprcsch.pdf
Extension Request12/30/2013Counsel for NGRID requests extension of time to 1/31/14 to file response to EFSB-PA-12http://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/123013ngexrq.pdf
 12/20/2013Presiding Officer advises parties that counsel for NGRID has advised him the engineering report relative to the railroad route alternative will not be filed by December 31, 2013 
Supplemental Responses12/19/2013Counsel for NGRID files supplemental response to EFSB-LU-4http://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/121913ngrdsprsp.pdf
 12/13/2013Transcript of Dec. 3rd procedural conference received from FAB 
Responses to EFSB-PA-912/4/2013Counsel for NGRID files supplemental response to EFSB-PA-9http://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/12413ngrsp.pdf
Email re procedural schedule12/3/2013Counsel for NH Transmission LLC forwards e-mail with no comment on procedural schedulehttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/12313nhtreml.pdf
Proposed Procedural Schedule12/3/2013Counsel for NGRID files proposed procedural schedule reflecting direct testimonyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/12313ngrdprsch.pdf
Email re Procedural Conference12/3/2013Counsel for NH Transmission forwards e-mail advising they will not be participating in Dec. 3rd procedural conferencehttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/12313nhtrnempc.pdf
Procedural Schedule12/3/2013Presiding Officer forwards procedural schedule and ground rules to partieshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/12313efsbpsch.pdf
Ground Rules12/3/2013Presiding Officer forwards procedural schedule and ground rules to partieshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/12313efsbgrul.pdf
Comments on Procedural Schedule12/2/2013Kristine Doll forwards e-mail with comments on procedural schedulehttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/12213krdllcmn.pdf
Proposed Procedural Schedule12/2/2013Counsel for Hawthorne Hotel, Finz Seafood & Grill and Waters & Brown, Inc, files proposed procedural schedule reflecting direct testimonyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/12213hhfpsc.pdf
Proposed Procedural Schedule11/27/2013Counsel for NGRID files proposed procedural schedules, one reflecting intervenor direct testimony and another with no such testimonyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/112713ngridpsc.pdf
Ruling11/27/2013Presiding Officer issues Ruling on Motion for Protective Treatmenthttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/112713efsbrul.pdf
 11/22/2013Tony Owens and Megan Hurst of Salem file comment letter 
Responses (Part 1 of 5)11/22/2013Counsel for NGRID files confidential and redacted responses to EFSB First Set of Information Requests together with Motion for Protective Treatment of EFSB-N-8, 12 and 15http://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/112213ngrefp1.pdf
Responses (Part 2 of 5)11/22/2013Counsel for NGRID files confidential and redacted responses to EFSB First Set of Information Requests together with Motion for Protective Treatment of EFSB-N-8, 12 and 15http://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/112213ngrefp2.pdf
Responses (Part 3 of 5)11/22/2013Counsel for NGRID files confidential and redacted responses to EFSB First Set of Information Requests together with Motion for Protective Treatment of EFSB-N-8, 12 and 15http://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/112213ngrefp3.pdf
Responses (Part 4 of 5)11/22/2013Counsel for NGRID files confidential and redacted responses to EFSB First Set of Information Requests together with Motion for Protective Treatment of EFSB-N-8, 12 and 15http://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/112213ngrefp4.pdf
Responses (Part 5 of 5)11/22/2013Counsel for NGRID files confidential and redacted responses to EFSB First Set of Information Requests together with Motion for Protective Treatment of EFSB-N-8, 12 and 15http://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/112213ngrefp5.pdf
 11/21/2013Maryann Curtin of Salem files letter of comment 
Ruling11/19/2013Presiding Officer issues Ruling on Petitions to Intervene and for Limited Participant Statushttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/111913efsbrul.pdf
Email11/15/2013Counsel for NGRID forwards e-mail advising it does not object to any intervention petitions filed to datehttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/111513ngrideml.pdf
 11/15/2013Transcript of Nov. 6th public hearing in Salem received from FAB 
 11/14/2013Sheryl Mackey of Salem files comments 
Cover Letter11/13/2013Counsel for Hawthorne Hotel, Finz Seafood & Grill and Waters & Brown, Inc, files Petition to Intervene and Notice of Appearance; and files comments of Salem Waterfront Hotel and Peabody Essex Museumhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/111313hwhtptcl.pdf
Petition to Intervene and Notice of Appearance11/13/2013Counsel for Hawthorne Hotel, Finz Seafood & Grill and Waters & Brown, Inc, files Petition to Intervene and Notice of Appearance; and files comments of Salem Waterfront Hotel and Peabody Essex Museumhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/111313hwhtptn.pdf
Comments by Timothy Clarke11/13/2013Timothy Clarke, Treasurer of Waters & Brown of Salem files commentshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/111313tmclkcmn.pdf
Petition for Limited Participation Status11/13/2013Rinus Oosthoek, Salem Chamber of Commerce, files petition for limited participation statushttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/111313sccmpt.pdf
Comments by Arthur Sargent11/13/2013Salem Councillor-at-Large, Arthur Sargent III, files commentshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/111313athhcmn.pdf
Petition for Limited Participant Status11/13/2013Timothy Clarke of Salem files petition for limited participation statushttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/111313tmclkptn.pdf
 11/13/2013Kathleen McCue Cullen of Salem files commentshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/111313kthcmn.pdf
Comments by Patricia Zaido11/12/2013Patricia Zaido, Exec. Dir. of Salem Partnership files commentshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/111213ptzcmn.pdf
 11/6/2013Salem City Solicitor files comments on the project 
 11/6/2013Counsel for NGRID files Return of Service relative to Nov. 6th public hearing 
Petition for Limited Participant Status11/5/2013Counsel for New Hampshire Transmission LLC files Petition for Limited Participation status along with Appearances of Counselhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/11513nhtptn.pdf
 11/4/2013Melanie McDonald of Salem files public comment letter 
Cover Letter11/4/2013Counsel for Footprint Power Salem Harbor Dev. LP files Petition to Intervene and Notice of Appearancehttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/11413fpptcl.pdf
Petition for Leave to Intervene11/4/2013Counsel for Footprint Power Salem Harbor Dev. LP files Petition to Intervene and Notice of Appearancehttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/11413fppt.pdf
Notice of Appearance11/4/2013Counsel for Footprint Power Salem Harbor Dev. LP files Petition to Intervene and Notice of Appearancehttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/11413fpptnt.pdf
 11/4/2013Mary Madore of Salem files letter in opposition to cable project and second request to intervene 
 11/1/2013Transcripts of October 22nd public hearing in Salem received from FAB 
Cover Letter11/1/2013Presiding Officer issues First Set of Information Requests to NGRIDhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/11113efsbir1cl.pdf
Information Request11/1/2013Presiding Officer issues First Set of Information Requests to NGRIDhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/11113efsbir1.pdf
EFSB Email10/31/2013Presiding Officer requests Kristine Doll to file an amended petition to intervene to conform with siting regulations and service on petitionerhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/103113efsbeml.pdf
Request to Intervene10/30/2013Kristine Doll of Salem forwards e-mail request to intervenehttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/103013krstdllrq.pdf
 10/24/2013Presiding Officer forwards recent letters of comment to NGRID 
Comments by Mayor Driscoll10/24/2013Mayor Driscoll of Salem files letter of comment to the Boardhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/102413mdcm.pdf
Comments by Kristine Doll10/22/2013Kristine Doll of Salem files letter of commenthttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/102213kdllcm.pdf
National Grid Map10/21/2013Mary Madore of Salem files letter of commenthttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/102113mmcma1.jpg
Project Map 210/21/2013Mary Madore of Salem files letter of commenthttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/102113mmcma2.jpg
Project Map 310/21/2013Mary Madore of Salem files letter of commenthttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/102113mmcma3.jpg
Ryan's new map10/21/2013Mary Madore of Salem files letter of commenthttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/102113mmcma4.jpg
Comments by Mary Madore10/21/2013Mary Madore of Salem files letter of commenthttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/102113mmcm.pdf
Comments by Jane Lyness10/21/2013Jane Lyness Wall of Salem files letter of commenthttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/102113jwllcm.pdf
Petition to Intervene10/18/2013Mayor Driscoll of Salem files Petition to Intervenehttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/101813slmptn.pdf
 10/10/2013Salem City Councillor Michael Sosnowski files comments 
State Rep Letter10/7/2013Notice of Public Hearing sent to Salem state senators and representatives; Interested Persons memo sent to Salem town officials and Adjudicatory Listhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/10713efsbsrplt.pdf
State Sen Letter10/7/2013Notice of Public Hearing sent to Salem state senators and representatives; Interested Persons memo sent to Salem town officials and Adjudicatory Listhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/10713efsbsslt.pdf
Interested Person Letter10/7/2013Notice of Public Hearing sent to Salem state senators and representatives; Interested Persons memo sent to Salem town officials and Adjudicatory Listhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/10713efsbiplt.pdf
Ruling9/30/2013Presiding Officer issues Ruling on Motion for Confidential Treatmenthttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/93013efsbrul.pdf
Ruling Red-lined Nondisclosure Agreement9/30/2013Presiding Officer issues Ruling on Motion for Confidential Treatmenthttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/93013efsbrulrd1.pdf
Ruling Red-lined Nondisclosure Agreement9/30/2013Presiding Officer issues Ruling on Motion for Confidential Treatmenthttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/93013efsbrulrd2.pdf
Cover Letter9/27/2013Counsel for NGRID files notices of public hearing in Salem in English, Spanish and Portuguese languageshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92713ngptcl.pdf
Spanish Legal Notice9/27/2013Counsel for NGRID files notices of public hearing in Salem in English, Spanish and Portuguese languageshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92713ngptlnsp.pdf
Salem Hearing Notice9/27/2013Counsel for NGRID files notices of public hearing in Salem in English, Spanish and Portuguese languageshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92713ngpthnt.pdf
Portuguese Legal Notice9/27/2013Counsel for NGRID files notices of public hearing in Salem in English, Spanish and Portuguese languageshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92713ngptlnpg.pdf
Order9/27/2013Presiding Officer forwards Consolidation Order issued by DPU Chair to partieshttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92713efsbord.pdf
Publication Letter9/23/2013Presiding Officer forwards Notice of Adjudication and Public Comment Hearing for publication and service on property owners and abuttershttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92313efsbntpl.pdf
Salem Hearing Notice9/23/2013Presiding Officer forwards Notice of Adjudication and Public Comment Hearing for publication and service on property owners and abuttershttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92313efsbnt.pdf
Please Read9/23/2013Presiding Officer forwards Notice of Adjudication and Public Comment Hearing for publication and service on property owners and abuttershttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92313efsbntpr.pdf
Cover Letter9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptcl.pdf
Petition9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptn.pdf
Exhibit 1 - Certified Salem Zoning Ordinance9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptex1.pdf
Exhibit 3 - Att. A9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptex3a.pdf
EFSB Map Book (part 8 of 13)9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptmb8.pdf
EFSB Map Book (part 9 of 13)9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptmb9.pdf
EFSB Map Book (part 10 of 13)9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptmb10.pdf
EFSB Map Book (part 11 of 13)9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptmb11.pdf
EFSB Map Book (part 12 of 13)9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptmb12.pdf
EFSB Map Book (part 13 of 13)9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptmb13.pdf
EFSB Map Book (part 2 of 13)9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptmb2.pdf
EFSB Map Book (part 3 of 13)9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptmb3.pdf
EFSB Map Book (part 4 of 13)9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptmb4.pdf
EFSB Map Book (part 5 of 13)9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptmb5.pdf
EFSB Map Book (part 6 of 13)9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptmb6.pdf
EFSB Map Book (part 7 of 13)9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptmb7.pdf
Exhibit 3 - Att .B9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptex3b.pdf
Exhibit 3 - Application Analysis9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptex3c.pdf
Exhibit 4 - Salem U-G Draft Hearing Notice9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptex4.pdf
Exhibit 5 - MEPA Affidavit9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptex5.pdf
Full Report with Appendices9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptin.pdf
EFSB Map Book (part 1 of 13)9/20/2013New England Power Company d/b/a NGRID files petitions for approval to construct and operate two new underground 115 kV transmission lines and related upgrades to existing Salem Harbor and Canal Street substations, and petition for certain zoning exemptions from the City of Salem Zoning Code, pursuant to G.L. c. 164, §69J, G.L. c.164, §72 and G.L. c.40A, §3, respectivelyhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptmb1.pdf
Cover Letter (confidential)9/20/2013Counsel for NGRID files confidential information related to its petition, Motion for Protective Treatment, Motion for Consolidation of Related Petitions, and Appearance of Counselhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptclf.pdf
Motion for Protective Treatment9/20/2013Counsel for NGRID files confidential information related to its petition, Motion for Protective Treatment, Motion for Consolidation of Related Petitions, and Appearance of Counselhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptmtpt.pdf
Motion to Consolidate - Section 69J9/20/2013Counsel for NGRID files confidential information related to its petition, Motion for Protective Treatment, Motion for Consolidation of Related Petitions, and Appearance of Counselhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptmtcn.pdf
Notices of Appearance D.P.U. 13-151, 13-152)9/20/2013Counsel for NGRID files confidential information related to its petition, Motion for Protective Treatment, Motion for Consolidation of Related Petitions, and Appearance of Counselhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptntap2.pdf
Motion to Consolidate - Section 72 and Zoning9/20/2013Counsel for NGRID files confidential information related to its petition, Motion for Protective Treatment, Motion for Consolidation of Related Petitions, and Appearance of Counselhttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptmtcn2pdf
Notices of Appearance (EFSB 13-2)9/20/2013Counsel for NGRID files of Appearances of Counsel, Section 72 checklist, zoning exemptions checklist, Draft Notice of Adjudication and Public Hearinghttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptntap.pdf
Salem U-G Draft Hearing Notice9/20/2013Counsel for NGRID files of Appearances of Counsel, Section 72 checklist, zoning exemptions checklist, Draft Notice of Adjudication and Public Hearinghttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngpthn.pdf
Section 72 and Zoning Petition Cover Letter9/20/2013Counsel for NGRID files of Appearances of Counsel, Section 72 checklist, zoning exemptions checklist, Draft Notice of Adjudication and Public Hearinghttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptzptcl.pdf
Section 72 Checklist9/20/2013Counsel for NGRID files of Appearances of Counsel, Section 72 checklist, zoning exemptions checklist, Draft Notice of Adjudication and Public Hearinghttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngpts72ckl.pdf
Section 72 Petition (D.P.U. 13-151)9/20/2013Counsel for NGRID files of Appearances of Counsel, Section 72 checklist, zoning exemptions checklist, Draft Notice of Adjudication and Public Hearinghttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngpts72pt.pdf
Zoning hecklist9/20/2013Counsel for NGRID files of Appearances of Counsel, Section 72 checklist, zoning exemptions checklist, Draft Notice of Adjudication and Public Hearinghttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptznckl.pdf
Zoning Petition (DPU 13-152)9/20/2013Counsel for NGRID files of Appearances of Counsel, Section 72 checklist, zoning exemptions checklist, Draft Notice of Adjudication and Public Hearinghttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptznpt.pdf
Section 72 and Zoning Petition cover letter9/20/2013Counsel for NGRID files of Appearances of Counsel, Section 72 checklist, zoning exemptions checklist, Draft Notice of Adjudication and Public Hearinghttp://www.env.state.ma.us/dpu/docs/siting/efsb13-2/13-151/152/92013ngptzpckcl.pdf