| Letter | 1/3/2013 | Siting Division Director advises NSTAR to comply with FAA requirements and concludes that no further inquiry by the EFSB is necessary regarding the project change | http://www.env.state.ma.us/dpu/docs/siting/efsb10-2a/1313efsblt.pdf |
| Responses to Siting Board | 12/21/2012 | Counsel for NSTAR files requested additional information relating to structures from Carver Substation and requests EFSB to approve additional changes | http://www.env.state.ma.us/dpu/docs/siting/efsb10-2a/122112nstrsp.pdf |
| Comments on Project Change | 12/19/2012 | Kerry LaLiberte files comments on project change | http://www.env.state.ma.us/dpu/docs/siting/efsb10-2a/121912kllbcm.pdf |
| Certificate of Service | 12/19/2012 | Kerry LaLiberte files comments on project change | http://www.env.state.ma.us/dpu/docs/siting/efsb10-2a/121912kllbcmcs.pdf |
| Letter re Questions | 12/14/2012 | Presiding Officer requests additional information from NSTAR relating to structures from Carver Substation to the State Forest Transition Station | http://www.env.state.ma.us/dpu/docs/siting/efsb10-2a/121412efsbltrq.pdf |
| Letter to D Rosen | 11/15/2012 | Siting Division Director advises NSTAR that further review of the project change relating to the State Forest to Plymouth Station line segment is not necessary | http://www.env.state.ma.us/dpu/docs/siting/efsb10-2a/111512efsbltr.pdf |
| NSTAR's Supplemental Materials | 11/13/2012 | Counsel for NSTAR files FAA’s determination of no hazard for structures 13A, 17A and 18A | http://www.env.state.ma.us/dpu/docs/siting/efsb10-2a/111312nstsmt.pdf |
| NSTAR's Response | 11/9/2012 | Counsel for NSTAR files requested information relative to pole heights, visual impacts, location of structures, notification to residents, original design violations and alternatives NSTAR has considered to raising pole heights | http://www.env.state.ma.us/dpu/docs/siting/efsb10-2a/11912nstrsp.pdf |
| Requests for Additional Information | 11/5/2012 | Presiding Officer requests additional information from NSTAR with regard to the proposed project change | http://www.env.state.ma.us/dpu/docs/siting/efsb10-2a/11512efsbrq.pdf |
| NSTAR's Comments | 11/2/2012 | Counsel for NSTAR forwards comments regarding the review process of its current project change | http://www.env.state.ma.us/dpu/docs/siting/efsb10-2a/11212nstcmpg.pdf |
| Letter | 11/1/2012 | Presiding officer forwards letter to counsel for NSTAR regarding proposed project change | http://www.env.state.ma.us/dpu/docs/siting/efsb10-2a/11112efsblt.pdf |
| Lower SEMA Construction Dates | 10/24/2012 | Counsel for NSTAR forwards expected construction start dates for the proposed project changes | http://www.env.state.ma.us/dpu/docs/siting/efsb10-2a/102412nstcnsd.pdf |
| PCF Supplement Filing | 10/18/2012 | Counsel for NSTAR files FAA’s determination of no hazard for structures 11-19, and a copy of NSTAR’s application to FAA for structures: 13A, 17A and 18A | http://www.env.state.ma.us/dpu/docs/siting/efsb10-2a/102412nstsupfl.pdf |
| PCF Supplement | 10/17/2012 | Counsel for NSTAR files an updated redesign of structures 11 through 19 in the form of a Project Change Supplement | http://www.env.state.ma.us/dpu/docs/siting/efsb10-2a/101712nstpcfsp.pdf |
| NSTAR Electric Lower SEMA Supplemental Filing | 9/24/2012 | Counsel for NSTAR files completed MOA to be inserted as Att. 4, Section 6 of Project Change Filing | http://www.env.state.ma.us/dpu/docs/siting/efsb10-2a/92412nstspfl.pdf |
| Project Change filing | 9/14/2012 | NSTAR Electric Company files a project change filing related to proposed modifications to the design of the 345-kV transmission line, proposed changes to the height and location of other ancillary structures in the area of Plymouth Municipal Airport and the towns of Carver, Plymouth, Bourne and Barnstable | http://www.env.state.ma.us/dpu/docs/siting/efsb10-2a/91412nstcmpfl.pdf |