The Official Website of the Executive Office of Energy and Environmental Affairs (EOEEA)
Docket:
Docket Details
TypeDocketNameSubjectSummaryFiledClosedCategory
SITING/DTE14-08NSTAR Electric CompanyPetition of NSTAR Electric Company to the Department of Public Utilities pursuant to G.L. c. 164, § 72, for approval for the construction of approximately 7.8 miles of new transmission line on existing NSTAR right-of-way between Barnstable Switching Station and the Harwich Tap in the towns of Barnstable, Yarmouth and Dennis.TRANSMISSION LINE2/4/2014  


Docket Electronic Filings
 DescriptionDateMemoURL
Order of Notice3/13/2014 Order of Notice and Notice of Adjudication and Public Comment Hearing forwarded to NSTAR for publication and service on owners and abuttershttp://www.env.state.ma.us/dpu/docs/electric/14-08/14-08-Notice-10095.pdf
Notice of Adjudication3/13/2014 Order of Notice and Notice of Adjudication and Public Comment Hearing forwarded to NSTAR for publication and service on owners and abuttershttp://www.env.state.ma.us/dpu/docs/electric/14-08/14-08-Notice-10096.pdf
 2/27/2014Hearing Officer, Steve August, assigned by DPU 
Revised Exhibits (part 1 of 3)2/19/2014NSTAR Electric Company submits revised Exhibits F and G to its initial filinghttp://www.env.state.ma.us/dpu/docs/electric/14-08/21914nstrvexp1.pdf
Revised Exhibits (part 2 of 3)2/19/2014NSTAR Electric Company submits revised Exhibits F and G to its initial filinghttp://www.env.state.ma.us/dpu/docs/electric/14-08/21914nstrvexp2.pdf
Revised Exhibits (part 3 of 3)2/19/2014NSTAR Electric Company submits revised Exhibits F and G to its initial filinghttp://www.env.state.ma.us/dpu/docs/electric/14-08/21914nstrvexp3.pdf
Cover Letter2/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstptcl.pdf
Petition2/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstptn.pdf
Motion for Protective Order2/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstptmt.pdf
Notices of Appearance2/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstptntap1.pdf
Notices of Appearance2/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstptntap2.pdf
Confidential Filing Cover Letter2/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstptclcf.pdf
Exhibit G2/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstptexg.pdf
Exhibit H2/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstptexh.pdf
Exhibit I2/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstptexi.pdf
Exhibit J2/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstptexj.pdf
Exhibit A2/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstptexa.pdf
Exhibit B2/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstptexb.pdf
Exhibit C2/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstptexc.pdf
Exhibit D2/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstptexd.pdf
Exhibit E2/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstptexe.pdf
Exhibit F2/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstptexf.pdf
Checklist for Section 722/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstptchl.pdf
Kevin McCune Resume2/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstptrskm.pdf
Kevin McCune Testimony2/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstpttskm.pdf
Kristen Trudell Resume (Att. A)2/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstptrskt.pdf
Kristen Trudell Direct Testimony2/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstpttskt.pdf
S. TourianTestimony2/4/2014NSTAR Electric Company files Petition for approval to construct approximately 7.8 miles of new transmission line on existing ROW between Barnstable Switching Station and Harwich Tap in the Towns of Barnstable, Yarmouth and Dennis, pursuant to G.L. c. 164, §72http://www.env.state.ma.us/dpu/docs/electric/14-08/2414nstpttsst.pdf
 2/4/2014NSTAR Electric Company files confidential copy of §72 petition and Exhibits B and C, along with Motion for Protective Treatment of same 





Docket Service List
FirstLastCompanyAddressCityStateZipEmailFAXPhone
CherylBlaine, Esq.Keegan Werlin LLP265 Franklin StreetBostonMA02110cblaine@keeganwerlin.com617-951-1354617-951-1400
CatherineKeuthen, Esq.Keegan Werlin LLP265 Franklin StreetBostonMA02110ckeuthen@keeganwerlin.com617-951-1354617-951-1400